Did it reach its goal?
Yes100%
Every deliverable done; the board approved the risk appetite.
A framework, policies and a single register for enterprise risk, with a board-approved risk appetite.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosurePhase 10 of 11
Next gate:Benefits Realization30 October 2026
Closing
Finish the open items and hand the benefits to their owner, then close the project. No project closes without lessons learned.
Seven mandatory items before any project closes.
Deliverables acceptedDone
Framework, policies and risk appetite approved by the board
Dr. Amal F. Al-SudairiDone 2026-08-31
Financial closureIn progress
Reconciling SAR 3.46M spend; closing the last SAR 40K of commitments
Haifa S. Al-RuwailiPlanned 2026-11-05
Contract closureDone
No external contracts — delivered in-house
Tariq S. Al-YamiDone 2026-09-10
Documents archivedIn progress
31 of 38 documents archived
Tariq S. Al-YamiPlanned 2026-11-02Evidence
Lessons learnedDone
One lesson published on sector champions
Tariq S. Al-YamiDone 2026-10-14Evidence
Benefits owner assignedNot started
Hand the response-plan benefit from the PM to the Deputy for Strategy
Dr. Amal F. Al-SudairiPlanned 2026-10-31
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
Did it reach its goal?
Yes100%
Every deliverable done; the board approved the risk appetite.
Did it stay on budget?
Yes−3.9%
SAR 3.46M against 3.6M, on time.
Were the benefits realised?
Partly78%
78% of risks have a response plan vs 90% targeted at 12 months.
What did we learn?
Yes1
One lesson published; a second proposed on linking the register to Munjaz.
What should improve?
Partly—
To complete in the post-closure review session.
1 lesson — offered automatically to similar projects when they are created.
Each benefit moves from the project manager to an owner who measures it after closure.
baseline 35 · now 78 · target 90 %