Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-030On track10ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.

Project managerTariq S. Al-YamiSponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosurePhase ⁦10⁩ of ⁦11⁩

Next gate:Benefits Realization30 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate20 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate5 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 April 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate3 June 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate16 June 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate19 July 2026Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate31 August 2026Closure · Current phaseClosure · Current phase
  11. Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026Benefits Realization · Not startedBenefits Realization · Not started
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close