PRJ-2026-030On track10ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.

Project managerTariq S. Al-YamiSponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosurePhase ⁦10⁩ of ⁦11⁩

Next gate:Benefits Realization30 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate20 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate5 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 April 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate3 June 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate16 June 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate19 July 2026Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate31 August 2026Closure · Current phaseClosure · Current phase
  11. Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026Benefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Enterprise Risk & Business Continuity Framework

APPROVEDV2Approved ⁦2025-03-07⁩

1Project identity

Project name
Enterprise Risk & Business Continuity Framework
Project code
PRJ-2026-030
Sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa
Project manager
Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa
Business owner
Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa
Portfolio & programme
Institutional Excellence & Governance Portfolio
Type & methodology
Consulting · Waterfall
Current phase
10Closure

2Background & rationale

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.

3Objectives

  1. 1Develop the organisational and information environment

4Scope

In scope

  • A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.
  • An approved method
  • Workshops with every sector

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1An approved method
  2. 2Workshops with every sector
  3. 3Knowledge transfer to the internal team

6Deliverables

1Project management plan⁦2025-03-31⁩
2Main deliverable — stage 1⁦2025-12-09⁩
3Main deliverable — final stage⁦2026-06-16⁩
4Final report⁦2026-08-31⁩

7Key milestones

  1. Charter approved⁦2025-03-07⁩
  2. Contract signed⁦2025-06-03⁩
  3. 50% of works complete⁦2025-12-09⁩
  4. Provisional acceptance⁦2026-07-19⁩
  5. Closure⁦2026-08-31⁩

8Budget

  • Main contract⁦72.2%⁩2.6M
  • Supervision & consulting⁦13.9%⁩500K
  • Internal team⁦8.3%⁩300K
  • Contingency reserve (⁦5%⁩)⁦5.6%⁩200K
The owning sector’s approved budgetTotal3.6M

9Timeline

Start
2025-03-099 Ramadan 1446 AH
Baseline finish
2026-08-3118 Rabiʻ I 1448 AH
Duration
⁦18⁩ months

10Key risks

  • No risks recorded yet.

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board