Enterprise Risk & Business Continuity Framework
Add to watchlistA framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosurePhase 10 of 11
Next gate:Benefits Realization30 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate20 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate5 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate21 April 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate3 June 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate16 June 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate19 July 2026Handover · CompleteHandover · Complete
- Gate into «Closure»DecisionConditional goDate31 August 2026Closure · Current phaseClosure · Current phase
- Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026Benefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-07-19 | 2025-08-03 | +15 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-29 | 2025-11-24 | +26 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-08 | 2026-03-16 | +36 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-05-21 | 2026-07-07 | +47 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-08-31 | 2026-10-26 | +56 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline030-D1 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2025-05-30 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting030-D2 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2025-07-19 | V1 | 2 of 2 |
| Deliverable: Current-state assessment030-D3 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2025-09-08 | V1 | 2 of 2 |
| Deliverable: Benchmarking030-D4 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2025-10-29 | V1 | 2 of 2 |
| Deliverable: Target model030-D5 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2025-12-19 | V1 | 2 of 2 |
| Deliverable: Roadmap030-D6 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2026-02-08 | V1 | 2 of 2 |