PRJ-2026-030On track10ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.

Project managerTariq S. Al-YamiSponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosurePhase ⁦10⁩ of ⁦11⁩

Next gate:Benefits Realization30 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate20 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate5 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 April 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate3 June 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate16 June 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate19 July 2026Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate31 August 2026Closure · Current phaseClosure · Current phase
  11. Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026Benefits Realization · Not startedBenefits Realization · Not started

Project lifecycle and its gates

Current phase: Closure. Pick a gate on the track to review it.

  1. Gate into «Feasibility»DecisionConditional goDate20 September 2024Mandatory criteria met, with points to close during the next phase.IdeaComplete
  2. Gate into «Initiation»DecisionGoDate8 January 2025All criteria and required documents met.FeasibilityComplete
  3. Gate into «Planning»DecisionGoDate9 March 2025All criteria and required documents met.InitiationComplete
  4. Gate into «Approval»DecisionGoDate5 April 2025All criteria and required documents met.PlanningComplete
  5. Gate into «Procurement»DecisionGoDate21 April 2025All criteria and required documents met.ApprovalComplete
  6. Gate into «Execution»DecisionConditional goDate3 June 2025Mandatory criteria met, with points to close during the next phase.ProcurementComplete
  7. Gate into «Monitoring & Control»DecisionGoDate16 June 2026All criteria and required documents met.ExecutionComplete
  8. Gate into «Handover»DecisionGoDate19 July 2026All criteria and required documents met.Monitoring & ControlComplete
  9. Gate into «Closure»DecisionConditional goDate31 August 2026Mandatory criteria met, with points to close during the next phase.HandoverComplete
  10. Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026ClosureCurrent phaseCurrent phase
  11. 11Benefits RealizationNot started
G9Next gateEPMO Committee

Closure gate — into benefits realisation

10Closure11Benefits RealizationPlanned for ⁦2026-10-30⁩In 2 days2026-10-3019 Jumada I 1448 AH
83/100

Gate readiness

Meets the pass mark

Automated control: no move until the criteria are met

  • ⁦1⁩ mandatory checklist item open
  • ⁦1⁩ required document not approved

Checklist

⁦3⁩ of ⁦4⁩ done

  • Final report approvedMandatory
  • Lessons learned capturedMandatory
  • Benefits owner and measurement planMandatory
  • Documents archivedMandatory

Required documents

⁦2⁩ of ⁦3⁩ approved

  • Final reportApproved · V1
  • Lessons-learned logNot submitted
  • Benefits measurement planApproved · V1

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Closure completeweight ⁦50⁩%Met

    Awaiting evidence from the project team.

  • Benefits measurement readyweight ⁦50⁩%Met

    Awaiting evidence from the project team.

Approvers

EPMO Committee

  • Dr. Noura M. Al-OtaibiEPMO directorVote pending
  • Dr. Mohammed I. Al-SubaieProject sponsorVote pending
  • Dr. Amal F. Al-SudairiBusiness ownerVote pending

Gate decision

The decision and its rationale go into the gate log and to the team.

What is the decision based on? It stays in the log.0 / 600