Enterprise Risk & Business Continuity Framework
Add to watchlistA framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosurePhase 10 of 11
Next gate:Benefits Realization30 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate20 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate5 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate21 April 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate3 June 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate16 June 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate19 July 2026Handover · CompleteHandover · Complete
- Gate into «Closure»DecisionConditional goDate31 August 2026Closure · Current phaseClosure · Current phase
- Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026Benefits Realization · Not startedBenefits Realization · Not started
Finance & earned value
The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.
Budget anatomy
The approved SAR 3.6M split into spent, committed and left, with the estimate at completion
- Actual spendSAR 3.5M
- Committed, not spentSAR 38K
- Allotted, uncommittedSAR 0
- Contingency availableSAR 108K
Budget
- Original budgetwhen the first baseline was approved
- SAR 3.6M
- Approved budgetafter approved change requests
- SAR 3.6M
- Current budgetavailable to spend now
- SAR 3.6M
- Revised budgetif the pending changes are approved
- SAR 3.6M
Commitments
- Commitmentssigned contracts and purchase orders
- SAR 3.5M
- Contracts0 active contracts
- SAR 0
- Purchase orders0 orders
- SAR 3.5M
- Remaining budgetapproved less actual
- SAR 138K
Spend & outlook
- Actual costincluding accruals
- SAR 3.5M
- Accrualswork done, not yet invoiced
- SAR 138K
- Estimate at completionthe PM’s bottom-up forecast
- SAR 3.5M
- ContingencySAR 72K drawn of SAR 180K
- SAR 108K
Budget bridge
From the original to the revised request
- Total
- Increase
- Decrease
Contingency draw-downs
SAR 72K drawn of SAR 180K
- Covering realised delivery risks2026-08-29SAR 72K
Cost breakdown structure
Every dimension adds up to the same totals
| Item | BudgetSAR M | CommittedSAR M | ActualSAR M | EACSAR M | VarianceSAR M | Consumption |
|---|---|---|---|---|---|---|
| 1Management & governance | 0.35 | 0.35 | 0.35 | 0.34 | +0.01 | |
| 2Diagnosis | 0.70 | 0.70 | 0.69 | 0.68 | +0.02 | |
| 3Design | 1.05 | 1.05 | 1.04 | 1.02 | +0.03 | |
| 4Implementation | 1.05 | 1.05 | 1.04 | 1.02 | +0.03 | |
| 5Handover & knowledge transfer | 0.35 | 0.35 | 0.35 | 0.34 | +0.01 | |
| Unallocated contingency | 0.11 | 0.00 | 0.00 | 0.05 | +0.05 | |
| Total | 3.60 | 3.50 | 3.46 | 3.46 | +0.14 |
Budget split
WBS
SAR 3.6M
Budget
- Management & governanceSAR 349.2K10%
- DiagnosisSAR 698.4K19%
- DesignSAR 1M29%
- ImplementationSAR 1M29%
- Handover & knowledge transferSAR 349.2K10%
- Unallocated contingencySAR 108K3%
Cash flow
Planned, committed, actual and forecast
Spend per period
SAR millions
- Planned
- Actual
- Forecast
Cumulative S-curve
Cumulative to close
- Actual, then forecast
- Planned, cumulative
- Committed, cumulative
Earned value management
At the data date 2026-10-28
Planned value, earned value and actual cost
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
1.00
On track
Schedule performance index
SPI = EV ÷ PV
1.04
On track
Cost performance index
CPI = EV ÷ AC
Finish by earned schedule
2026-08-31
SPI(t) 1.00 against the approved finish 2026-08-31
- Planned valuePV
- SAR 3.6M
- The value of the work that should be done by today.
- PV
- Earned valueEV
- SAR 3.6M
- The value of the work actually done, at plan prices.
- EV = % complete × BAC
- Actual costAC
- SAR 3.5M
- What has actually been spent on the work done.
- AC
- Budget at completionBAC
- SAR 3.6M
- The approved budget for the whole project.
- BAC
- Cost varianceCV
- +0.14 SAR M
- Earned less actual; negative means paying more than the value.
- CV = EV − AC
- Schedule varianceSV
- +0.00 SAR M
- Earned less planned; negative means behind, in value.
- SV = EV − PV
- Cost performance indexCPI
- 1.04
- Value produced per riyal spent; under 1 is an overrun.
- CPI = EV ÷ AC
- Schedule performance indexSPI
- 1.00
- Work done over work planned; under 1 is behind.
- SPI = EV ÷ PV
- Estimate at completionEAC
- SAR 3.5M
- What the project will cost when it finishes, as forecast.
- EAC = BAC ÷ CPI
- Estimate to completeETC
- SAR 0
- What is still to be spent to completion.
- ETC = EAC − AC
- Variance at completionVAC
- +0.14 SAR M
- Budget less the estimate; negative is an overrun.
- VAC = BAC − EAC
- To-complete performance indexTCPI
- 0.00
- The cost efficiency the rest must reach to stay on budget.
- TCPI = (BAC − EV) ÷ (BAC − AC)
Automatic end-of-project forecast
Four ways to estimate the final cost, and the date earned schedule points to
- At today’s cost performanceSAR 3.5M
- If the rest goes to planSAR 3.5M
- At cost and schedule performanceSAR 3.5M
- The PM’s bottom-up estimateSAR 3.5M
- The performance needed on the rest is below what has been achieved; the budget holds.
Estimate at completion at that performance
SAR 3.5M
Variance at completion: +0.14 SAR M