PRJ-2026-030On track10ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the President.

Project managerTariq S. Al-YamiSponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosurePhase ⁦10⁩ of ⁦11⁩

Next gate:Benefits Realization30 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate20 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate5 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 April 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate3 June 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate16 June 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate19 July 2026Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate31 August 2026Closure · Current phaseClosure · Current phase
  11. Gate into «Benefits Realization»DecisionNot held yetDate30 October 2026Benefits Realization · Not startedBenefits Realization · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work3.5M⁦15⁩ elements
Unallocated contingency108KSAR 180K
Budget at completion3.6MPRJ-2026-030
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project596⁦2025-03-09⁩⁦2026-10-26⁩⁦100%⁩3.493.46—
1
Phase147⁦2025-03-09⁩⁦2025-08-03⁩⁦100%⁩0.350.35—
1.1
WBS element90⁦2025-03-09⁩⁦2025-06-07⁩⁦100%⁩0.170.170 / 1
1.2
WBS element91⁦2025-05-04⁩⁦2025-08-03⁩⁦100%⁩0.170.171 / 2
2
Phase147⁦2025-06-30⁩⁦2025-11-24⁩⁦100%⁩0.700.69—
2.1
WBS element90⁦2025-06-30⁩⁦2025-09-28⁩⁦100%⁩0.350.351 / 1
2.2
WBS element91⁦2025-08-25⁩⁦2025-11-24⁩⁦100%⁩0.350.351 / 2
3
Phase146⁦2025-10-21⁩⁦2026-03-16⁩⁦100%⁩1.051.04—
3.1
WBS element90⁦2025-10-21⁩⁦2026-01-19⁩⁦100%⁩0.520.521 / 1
3.2
WBS element90⁦2025-12-16⁩⁦2026-03-16⁩⁦100%⁩0.520.521 / 2
4
Phase147⁦2026-02-10⁩⁦2026-07-07⁩⁦100%⁩1.051.04—
4.1
WBS element91⁦2026-02-10⁩⁦2026-05-12⁩⁦100%⁩0.520.521 / 1
4.2
WBS element90⁦2026-04-08⁩⁦2026-07-07⁩⁦100%⁩0.520.521 / 2
5
Phase145⁦2026-06-03⁩⁦2026-10-26⁩⁦100%⁩0.350.35—
5.1
WBS element91⁦2026-06-03⁩⁦2026-09-02⁩⁦100%⁩0.170.171 / 1
5.2
WBS element88⁦2026-07-30⁩⁦2026-10-26⁩⁦100%⁩0.170.171 / 1
Total⁦100%⁩3.493.46