Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 25
- Date
- 2026-10-13
- Hijri
- 2 Jumada I 1448 AH
- Reference
- PAY-2026-019
Interim payment certificate no. (25)
For the work of September 2026
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 381,300,000 |
| 2 | Less: previous certificates | (371,500,000) |
| 3 | Value of work in this certificate | 9,800,000 |
| 4 | Less: retention (10%) | (980,000) |
| 5 | Less: advance payment recovery (10%) | (980,000) |
| 6 | Less: delay and breach penalties | (1,250,000) |
| 7 | Total deductions | (3,210,000) |
| 8 | Net before VAT | 6,590,000 |
| 9 | Add: value added tax (15%) | 988,500 |
| 10 | Net amount payable to the contractor | 7,578,500 |
Amount in words: Seven million five hundred seventy-eight thousand five hundred Saudi riyals only
Retention held up to this certificate: SAR 38.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 40,137,000 | 743,000 | 40,880,000 | 100% |
| Earthworks & foundations | 105,120,000 | 103,010,000 | 2,110,000 | 105,120,000 | 100% |
| Concrete & structural works | 181,040,000 | 138,034,000 | 3,657,000 | 141,691,000 | 78% |
| Mechanical, electrical & plumbing | 140,160,000 | 61,915,000 | 2,143,000 | 64,058,000 | 46% |
| Finishes & external works | 87,600,000 | 24,754,000 | 984,000 | 25,738,000 | 29% |
| Testing & commissioning | 29,200,000 | 3,650,000 | 163,000 | 3,813,000 | 13% |
| Total | 584,000,000 | 371,500,000 | 9,800,000 | 381,300,000 | 65% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani