Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 24
- Date
- 2026-09-13
- Hijri
- 2 Rabiʻ II 1448 AH
- Reference
- PAY-2026-009
Interim payment certificate no. (24)
For the work of August 2026
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 371,500,000 |
| 2 | Less: previous certificates | (360,400,000) |
| 3 | Value of work in this certificate | 11,100,000 |
| 4 | Less: retention (10%) | (1,110,000) |
| 5 | Less: advance payment recovery (10%) | (1,110,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,220,000) |
| 8 | Net before VAT | 8,880,000 |
| 9 | Add: value added tax (15%) | 1,332,000 |
| 10 | Net amount payable to the contractor | 10,212,000 |
Amount in words: Ten million two hundred twelve thousand Saudi riyals only
Retention held up to this certificate: SAR 37.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 39,998,000 | 882,000 | 40,880,000 | 100% |
| Earthworks & foundations | 105,120,000 | 102,629,000 | 2,491,000 | 105,120,000 | 100% |
| Concrete & structural works | 181,040,000 | 130,259,000 | 4,038,000 | 134,297,000 | 74% |
| Mechanical, electrical & plumbing | 140,160,000 | 60,005,000 | 2,407,000 | 62,412,000 | 45% |
| Finishes & external works | 87,600,000 | 23,976,000 | 1,100,000 | 25,076,000 | 29% |
| Testing & commissioning | 29,200,000 | 3,533,000 | 182,000 | 3,715,000 | 13% |
| Total | 584,000,000 | 360,400,000 | 11,100,000 | 371,500,000 | 64% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani