Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦24⁩ — August 2026

Riyadh Administrative Court building — civil & MEP works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
24
Date
⁦2026-09-13⁩
Hijri
2 Rabiʻ II 1448 AH
Reference
PAY-2026-009

Interim payment certificate no. (⁦24⁩)

For the work of August 2026

Contract number
BOG/2024/006
Etimad reference
2401430082
Contract
Riyadh Administrative Court building — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
Riyadh Administrative Court Building
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
560,000,000
Current contract value
584,000,000including variations of SAR 24M

Certificate summary (SAR)

1Total value of work completed to date371,500,000
2Less: previous certificates(360,400,000)
3Value of work in this certificate11,100,000
4Less: retention (⁦10%⁩)(1,110,000)
5Less: advance payment recovery (⁦10%⁩)(1,110,000)
6Less: delay and breach penalties0
7Total deductions(2,220,000)
8Net before VAT8,880,000
9Add: value added tax (15%)1,332,000
10Net amount payable to the contractor10,212,000

Amount in words: Ten million two hundred twelve thousand Saudi riyals only

Retention held up to this certificate: SAR 37.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation40,880,00039,998,000882,00040,880,000⁦100%⁩
Earthworks & foundations105,120,000102,629,0002,491,000105,120,000⁦100%⁩
Concrete & structural works181,040,000130,259,0004,038,000134,297,000⁦74%⁩
Mechanical, electrical & plumbing140,160,00060,005,0002,407,00062,412,000⁦45%⁩
Finishes & external works87,600,00023,976,0001,100,00025,076,000⁦29%⁩
Testing & commissioning29,200,0003,533,000182,0003,715,000⁦13%⁩
Total584,000,000360,400,00011,100,000371,500,000⁦64%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-09-13⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-09-15⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2026-09-18⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-09-21⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-09-24⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-09-13⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-09-15⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-09-18⁩

    Eng. Shahad M. Al-Malki · Director, Judicial Buildings & Premises

    Took 3 days

  4. Payment order prepared⁦2026-09-21⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-24⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Dr. Abdullah S. Al-Qahtani

Certificate history

24 September 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-09-24 13:00

21 September 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-09-21 13:00

18 September 2026

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2026-09-18 13:00

15 September 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-09-15 13:00

13 September 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-09-13 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close