Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 21
- Date
- 2026-05-27
- Hijri
- 10 Dhuʻl-Hijjah 1447 AH
- Reference
- PAY-2024-006-21
Interim payment certificate no. (21)
For the work of May 2026
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 345,380,000 |
| 2 | Less: previous certificates | (333,790,000) |
| 3 | Value of work in this certificate | 11,590,000 |
| 4 | Less: retention (10%) | (1,159,000) |
| 5 | Less: advance payment recovery (10%) | (1,159,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,318,000) |
| 8 | Net before VAT | 9,272,000 |
| 9 | Add: value added tax (15%) | 1,390,800 |
| 10 | Net amount payable to the contractor | 10,662,800 |
Amount in words: Ten million six hundred sixty-two thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 34.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 39,840,000 | 1,040,000 | 40,880,000 | 100% |
| Earthworks & foundations | 105,120,000 | 99,125,000 | 2,809,000 | 101,934,000 | 97% |
| Concrete & structural works | 181,040,000 | 113,783,000 | 3,992,000 | 117,775,000 | 65% |
| Mechanical, electrical & plumbing | 140,160,000 | 55,568,000 | 2,456,000 | 58,024,000 | 41% |
| Finishes & external works | 87,600,000 | 22,203,000 | 1,110,000 | 23,313,000 | 27% |
| Testing & commissioning | 29,200,000 | 3,271,000 | 183,000 | 3,454,000 | 12% |
| Total | 584,000,000 | 333,790,000 | 11,590,000 | 345,380,000 | 59% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani