PRJ-2026-009At risk7ExecutionHybrid

Migration to the Government Cloud

Add to watchlist

Move 46 systems to the government cloud under the classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩

Planned ⁦53%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control1 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−8

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦47%⁩ done against ⁦53%⁩ planned.

SPI ⁦0.89⁩, CPI ⁦0.97⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦79%⁩ of budget

25.2M/ 52M1.6Mprojected overrun(⁦3.1%⁩)
Actual spend
25.2M
Committed
41M
Approved budget
52M
Estimate at completion
53.6M

Next milestones

  • Provisional acceptance⁦2027-01-24⁩was ⁦2027-01-08⁩At risk
  • Closure⁦2027-03-21⁩was ⁦2027-02-28⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 2.6M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0029Cloud consumption costs above estimateProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦1⁩ of ⁦4⁩ approved

  • Project management planDLV-009-1 · V1Eng. Omar H. Bawazir⁦2025-06-27⁩2025-06-272 Muharram 1447 AHApproved
  • Main deliverable — stage 1DLV-009-2 · V1Eng. Nayef H. Al-Buqami189 days overdue2026-04-225 Dhuʻl-Qiʻdah 1447 AHIn review
  • Main deliverable — final stageDLV-009-3 · V1Eng. Nayef H. Al-BuqamiIn 34 days2026-12-0121 Jumada II 1448 AHIn progress
  • Final reportDLV-009-4 · V0Eng. Nayef H. Al-BuqamiIn 123 days2027-02-2821 Ramadan 1448 AHDraft

Team, contracts & documents

Team

3 members

Eng. Omar H. Bawazir · Director, IT InfrastructureEng. Nayef H. Al-Buqami · Deputy, Technology InfrastructureEng. Saad M. Al-Dosari · Cloud & Integration Engineer
  • Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureProject managerP-024o.bawazir@alwaha.gov.sa⁦40%⁩
  • Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDeputy, Technology InfrastructureProject sponsorP-017n.albuqami@alwaha.gov.sa⁦20%⁩
  • Eng. Saad M. Al-DosariEng. Saad M. Al-DosariCloud & Integration EngineerSystem migration to the cloudP-034sa.aldosari@alwaha.gov.sa⁦30%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close