PRJ-2026-009At risk7ExecutionHybrid

Judicial Systems Migration to the Government Cloud

Add to watchlist

Move 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩

Planned ⁦53%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control1 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

3 members, about ⁦0.9⁩ full-time equivalents

Leadership

2 members

  • Eng. Omar H. BawazirProject manager⁦40%⁩Allocated ⁦115%⁩ across all projectsA
  • Eng. Nayef H. Al-BuqamiProject sponsor⁦20%⁩R

Core team

1 member

  • Eng. Saad M. Al-DosariJudicial systems migration to the cloud⁦30%⁩R

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦3⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Majed S. Al-RasheedManage closelyEng. Nayef H. Al-BuqamiManage closelyProjects Follow-up Office (EPMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedKingdom Cloud IT Co.Manage closely

Interest

Project sponsor

Eng. Majed S. Al-Rasheed

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-18⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Majed S. Al-RasheedProject sponsorDecisions and fundingSupportiveLeadingEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa⁦2026-10-18⁩
Eng. Nayef H. Al-BuqamiBusiness ownerAccepts deliverables, owns benefitsLeadingEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa⁦2026-10-21⁩
Projects Follow-up Office (EPMO)GovernanceCompliance and data qualitySupportiveEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa⁦2026-10-15⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@bog.gov.sa⁦2026-10-12⁩
Kingdom Cloud IT Co.Main vendorDelivers the contracted workLeadingEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa⁦2026-10-22⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa⁦2026-09-24⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Omar H. Bawazir⁦2026-11-13⁩
  • Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Omar H. Bawazir⁦2026-11-01⁩
  • EPMOData and indicator updatesWeeklyDashboardEng. Omar H. Bawazir⁦2026-10-29⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Omar H. BawazirAt launch

Coming up

By date

  1. 292026-10EPMODashboard · Weekly
  2. 012026-11Business ownerEmail · Fortnightly
  3. 132026-11Project sponsorMeeting · Monthly