PRJ-2026-009At risk7ExecutionHybrid

Judicial Systems Migration to the Government Cloud

Add to watchlist

Move 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩

Planned ⁦53%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control1 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 52M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 1.6M
EAC SAR 53.6M
Revised request SAR 52M
  • Actual spendSAR 25.2M
  • Committed, not spentSAR 15.8M
  • Allotted, uncommittedSAR 9.4M
  • Contingency availableSAR 1.6M

Budget

Original budgetwhen the first baseline was approved
SAR 52M
Approved budgetafter approved change requests
SAR 52M
Current budgetavailable to spend now
SAR 52M
Revised budgetif the pending changes are approved
SAR 52M

Commitments

Commitmentssigned contracts and purchase orders
SAR 41M
Contracts1 active contract
SAR 38M
Purchase orders⁦0⁩ orders
SAR 3M
Remaining budgetapproved less actual
SAR 26.8M

Spend & outlook

Actual costincluding accruals
SAR 25.2M
Accrualswork done, not yet invoiced
SAR 1M
Estimate at completionthe PM’s bottom-up forecast
SAR 53.6M
ContingencySAR 1M drawn of SAR 2.6M
SAR 1.6M

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 1M drawn of SAR 2.6M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 1M

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance4.044.294.294.29⁦−0.25⁩
2Analysis & design8.579.119.119.11⁦−0.54⁩
3Build20.1816.8811.7920.69⁦−0.51⁩
4Testing & acceptance10.096.120.0010.71⁦−0.62⁩
5Launch & handover7.574.590.008.03⁦−0.46⁩
Unallocated contingency1.560.000.000.78⁦+0.78⁩
Total52.0041.0025.2053.61⁦−1.61⁩

Budget split

WBS

SAR 52M

Budget

  • Management & governanceSAR 4M⁦8%⁩
  • Analysis & designSAR 8.6M⁦16%⁩
  • BuildSAR 20.2M⁦39%⁩
  • Testing & acceptanceSAR 10.1M⁦19%⁩
  • Launch & handoverSAR 7.6M⁦15%⁩
  • Unallocated contingencySAR 1.6M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-10⁩+437

SPI(t) ⁦0.59⁩ against the approved finish ⁦2027-02-28⁩

Planned valuePV
SAR 47.1M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 24.4M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 25.2M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 52M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.76⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−22.62⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.97
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.52
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 53.6M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 28.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−1.61⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.03
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 53.6M
  • If the rest goes to planSAR 52.8M
  • At cost and schedule performanceSAR 79.9M
  • The PM’s bottom-up estimateSAR 53.6M
  • To stay within SAR 52M, cost performance on the rest must rise to ⁦1.03⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 53.6M

Variance at completion: ⁦−1.61⁩ SAR M