Judicial Systems Migration to the Government Cloud
Add to watchlistMove 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.
Budget (BAC)
Actual cost
48% of budget
Progress
Planned 53%
Estimate at completion
SAR +1.6M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control1 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
Move 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.
In scope
- Move 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.
- Migration from legacy systems
- ERP integration
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2025-06-30
Baseline approved at the planning gate
Budget52MFinish2027-02-28
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical2
- Regulatory1
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
33%
2/6 · test result is a pass
Accepted
33%
2/6 · signed off by the business owner
Display options
| REQ-009-01 | One system for the procedures | Business | Must | In progress | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | SB-1 | |
| REQ-009-02 | Historical data migration | Technical | Must | In progress | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | SB-1 | |
| REQ-009-03 | Ready operational reports | Functional | Must | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | SB-1 | |
| REQ-009-04 | ERP integration | Technical | Should | In progress | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | SB-1 | |
| REQ-009-05 | Data classification | Regulatory | Should | In progress | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | SB-1 | |
| REQ-009-06 | Identity and access management | Security | Could | In progress | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. No requirement has a gap.