Judicial Systems Migration to the Government Cloud
Add to watchlistMove 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.
Budget (BAC)
Actual cost
48% of budget
Progress
Planned 53%
Estimate at completion
SAR +1.6M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control1 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate13 December 2024All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate2 April 2025All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionConditional goDate1 June 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
- Gate into «Approval»DecisionGoDate3 July 2025All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate22 July 2025All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionConditional goDate11 September 2025Mandatory criteria met, with points to close during the next phase.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 1 required document not approved
- Weighted score 72 under the pass mark 75
Checklist
4 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Users trained — judges, clerks and staff
- Launch rollback plan
Required documents
3 of 4 approved
- UAT reportApproved · V1
- Penetration test reportApproved · V1
- Operations & support planApproved · V1
- Data migration reconciliationNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Met
Awaiting evidence from the project team.
Quality & securityweight 30%Met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Eng. Nayef H. Al-BuqamiBusiness ownerVote pending