Portfolio · PF-TECH

Technology Projects Portfolio

At risk

Technology infrastructure, cloud, cybersecurity and enterprise systems.

What-if scenarios
Approved budget
SAR 365M

incl. SAR 12.3M unallocated reserve

Actual spend
SAR 245.7M

⁦67%⁩ of budget

EAC
SAR 376M+3.0%

Estimate at completion

Expected value
SAR 520M

⁦17%⁩ realised

Health score
71−3

was ⁦74⁩ in May

Manager

Eng. Nayef H. Al-Buqami

Deputy, Technology Infrastructure

Owner

Eng. Majed S. Al-Rasheed

VP, Digital Transformation & Technology

AI insight

⁦4⁩ projects in this portfolio are pulling its health down

Most of it comes from “Enterprise Resource Planning (ERP) System” (SPI ⁦0.82⁩) and “Migration to the Government Cloud” (SPI ⁦0.89⁩). Fixing those two lifts the portfolio towards ⁦80⁩ within two quarters.

Confidence⁦81%⁩

Portfolio health & performance

The health score from eight weighted dimensions (§61), and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

71At risk
DimensionScoreWeightPoints
Schedule66⁦20%⁩13.2
Cost74⁦20%⁩14.8
Risk58⁦15%⁩8.7
Scope78⁦10%⁩7.8
Quality80⁦10%⁩8.0
Resources67⁦10%⁩6.7
Stakeholders76⁦5%⁩3.8
Benefits80⁦10%⁩8.0
Total71

Health-score trend

May – October 2026

7471

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

§133 — risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • On track
  • At risk
  • Off track
Approved budget · SAR 148M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1Enterprise Cybersecurity ProgrammePRJ-2026-005·Priority score 85On track
  2. 2National Backup Data CentrePRJ-2026-003·Priority score 82At risk
  3. 3Migration to the Government CloudPRJ-2026-009·Priority score 77At risk
  4. 4Enterprise Resource Planning (ERP) SystemPRJ-2026-001·Priority score 74Off track
  5. 5Smart Asset Management SystemPRJ-2026-011·Priority score 66On track
  6. 6Document & Correspondence Management PlatformPRJ-2026-017·Priority score 62At risk

Portfolio priorities 2026–2027

  • Recover the ERP programmeOff track at SPI 0.82 and blocking the asset-management system.
  • Host 50% of systems on the government cloudConditional on the backup data centre being ready.
  • Full compliance with the NCA Essential Cybersecurity Controls91% today against a 95% target.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 365MSAR 365M
Unallocated reserve−SAR 12.3MSAR 352.7M
Digital Infrastructure Programme+SAR 15.1MSAR 367.8M
Enterprise Systems Programme+SAR 8.2MSAR 376M
Estimate at completionSAR 376MSAR 376M

Budget use

245.7M/ 365M11Mprojected overrun(⁦3.0%⁩)
Actual spend
245.7M
Committed
294.8M
Approved budget
365M
Estimate at completion
376M

Expected-value mix

Expected-value mix

SAR 520M

Expected value

  • Cost savingSAR 208M⁦40%⁩
  • ProductivitySAR 187.2M⁦36%⁩
  • Time savedSAR 72.8M⁦14%⁩
  • Beneficiary satisfactionSAR 52M⁦10%⁩
Expected-value mix
CategoryValueShare
Cost savingSAR 208M⁦40%⁩
ProductivitySAR 187.2M⁦36%⁩
Time savedSAR 72.8M⁦14%⁩
Beneficiary satisfactionSAR 52M⁦10%⁩
TotalSAR 520M⁦100%⁩

SAR 88.7M

Expected value SAR 520M

⁦92%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects (§6). Click a project for a quick look.

⁦7⁩ results
Export CSV
National Backup Data CentrePRJ-2026-003PG-037ExecutionAt risk⁦72%⁩148M162.6M⁦+9.9%⁩0.90Schedule performance index · 0.900.91Cost performance index · 0.91Risk score · Weak
Enterprise Resource Planning (ERP) SystemPRJ-2026-001PG-047ExecutionOff track⁦61%⁩64.5M73.3M⁦+13.6%⁩0.82Schedule performance index · 0.820.88Cost performance index · 0.88Risk score · Weak
Migration to the Government CloudPRJ-2026-009PG-037ExecutionAt risk⁦47%⁩52M53.6M⁦+3.1%⁩0.89Schedule performance index · 0.890.97Cost performance index · 0.97Risk score · Fair
Enterprise Cybersecurity ProgrammePRJ-2026-005PG-038Monitoring & ControlOn track⁦88%⁩38.6M37.5M⁦−2.9%⁩1.02Schedule performance index · 1.021.03Cost performance index · 1.03Risk score · Good
Smart Asset Management SystemPRJ-2026-011PG-044PlanningOn track⁦6%⁩24M24M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Good
Document & Correspondence Management PlatformPRJ-2026-017PG-049HandoverAt risk⁦95%⁩14.2M14.2M⁦0.0%⁩0.95Schedule performance index · 0.951.00Cost performance index · 1.00Risk score · Good
HR Self-Service AutomationPRJ-2026-032PG-0411Benefits RealizationOn track⁦100%⁩11.4M10.8M⁦−5.7%⁩1.00Schedule performance index · 1.001.06Cost performance index · 1.06Risk score · Excellent
Total · 7352.7M376M
⁦1⁩–⁦7⁩ of ⁦7⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Open-risk heat map

8 risks

Latest on this portfolio

14 October 2026

  1. Approval: PMO Committee Rework DEC-2026-038ERP project plan sent back for rework