RSK-0012Enterprise Resource Planning (ERP) System
Customisation and Etimad integration costs exceeding the approved contingency
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Customisations missed in the tender book, and an Etimad integration harder than expected
Preventive controls
- Freeze all non-mandatory customisations
- Change request to raise the customisation & integration budget
- Independent review of the vendor’s estimates
1 / 3
Event
Customisation and Etimad integration costs exceeding the approved contingency
The budget increase is refused, or spend passes 95% of contingency
Contingency
Move the asset module to the Smart Asset Management project
Impact
The contingency fully consumed and SAR 6.8M of extra budget requested
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 6.8M
Residual
44% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 5 days ago
Project manager
Dana S. Al-Saleh
Currently followed up hereProgramme manager
Current levelDana S. Al-Saleh
Automatically at 15 days unreviewed · in 10 days- 3
PMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 15 days - 4
Executive committee
Eng. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Freeze all non-mandatory customisations
Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.saDone2026-10-302026-10-3019 Jumada I 1448 AHChange request to raise the customisation & integration budget
Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.saDone2026-10-092026-10-0928 Rabiʻ II 1448 AHIndependent review of the vendor’s estimates
Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@alwaha.gov.saIn progressIn 11 days2026-11-0828 Jumada I 1448 AH
Trigger
The budget increase is refused, or spend passes 95% of contingency
Contingency
Move the asset module to the Smart Asset Management project