Enterprise Resource Planning (ERP) System
Remove from watchlistOne integrated system for finance, procurement and HR, connected to the Etimad platform.
Budget (BAC)
Actual cost
69% of budget
Progress
Planned 74%
Estimate at completion
SAR +8.8M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started