10My actionsNotifications
PRJ-2026-001Off track7ExecutionHybrid

Enterprise Resource Planning (ERP) System

Remove from watchlist

One integrated system for finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩

Planned ⁦74%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control21 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close