Enterprise Resource Planning (ERP) System
Remove from watchlistOne integrated system for finance, procurement and HR, connected to the Etimad platform.
Budget (BAC)
Actual cost
69% of budget
Progress
Planned 74%
Estimate at completion
SAR +8.8M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+58 days vs approved
- Critical activities
- 6
- of 8 open activities
- Late activities
- 5
- past their baseline finish
- Schedule performance
- 0.62
- earned ÷ planned value
- Next milestone
- in 30 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 8 open activities, data date 2026-10-28
“Integrations” needs a pace 4.0× faster than it has kept
It earned 70% in 283 days; the forecast assumes the rest in 30 days. At the pace so far it finishes on 2027-02-26.
Milestones slip 135 days on average
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance