PRJ-2026-001Off track7ExecutionHybrid

Enterprise Resource Planning (ERP) System

Remove from watchlist

One integrated system for finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩

Planned ⁦74%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control21 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+58⁩ days vs approved

Original baseline⁦2026-12-31⁩
Approved baseline⁦2026-12-31⁩
Current forecast⁦2027-02-27⁩
By earned schedule⁦2028-03-04⁩
Critical activities
6
of ⁦8⁩ open activities
Late activities
5
past their baseline finish
Schedule performance
0.62
earned ÷ planned value
Next milestone
in 30 days
Build complete
Expand allCollapse all
Activity
Enterprise Resource Planning (ERP) SystemPlanned: ⁦2025-01-12⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-01-12⁩ → ⁦2027-02-27⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-01-12⁩ → ⁦2025-06-22⁩Actual: ⁦2025-01-12⁩ → ⁦2025-09-26⁩
Project plan & baselinePlanned: ⁦2025-01-12⁩ → ⁦2025-04-21⁩Actual: ⁦2025-01-12⁩ → ⁦2025-06-19⁩
Monitoring & reportingPlanned: ⁦2025-03-15⁩ → ⁦2025-06-22⁩Actual: ⁦2025-04-21⁩ → ⁦2025-09-26⁩
Project plan approvedPlanned: ⁦2025-06-22⁩ → ⁦2025-06-22⁩Actual: ⁦2025-09-26⁩ → ⁦2025-09-26⁩Project plan approved
Analysis & designPlanned: ⁦2025-05-16⁩ → ⁦2025-10-24⁩Actual: ⁦2025-07-29⁩ → ⁦2026-04-12⁩
Business requirementsPlanned: ⁦2025-05-16⁩ → ⁦2025-08-23⁩Actual: ⁦2025-07-29⁩ → ⁦2026-01-03⁩
Solution designPlanned: ⁦2025-07-17⁩ → ⁦2025-10-24⁩Actual: ⁦2025-11-05⁩ → ⁦2026-04-12⁩
Designs approvedPlanned: ⁦2025-10-24⁩ → ⁦2025-10-24⁩Actual: ⁦2026-04-12⁩ → ⁦2026-04-12⁩Designs approved
BuildPlanned: ⁦2025-09-17⁩ → ⁦2026-04-27⁩Forecast: ⁦2026-01-18⁩ → ⁦2026-11-27⁩Float: ⁦0⁩d
Release 1Planned: ⁦2025-09-17⁩ → ⁦2025-12-25⁩Actual: ⁦2026-02-12⁩ → ⁦2026-07-20⁩
Release 2Planned: ⁦2025-11-17⁩ → ⁦2026-02-25⁩Actual: ⁦2026-05-22⁩ → ⁦2026-10-27⁩
IntegrationsPlanned: ⁦2026-01-18⁩ → ⁦2026-04-27⁩Forecast: ⁦2026-01-18⁩ → ⁦2026-11-27⁩Float: ⁦0⁩d+214
Build completePlanned: ⁦2026-04-27⁩ → ⁦2026-04-27⁩Forecast: ⁦2026-11-27⁩ → ⁦2026-11-27⁩Float: ⁦92⁩dBuild complete
Testing & acceptancePlanned: ⁦2026-03-21⁩ → ⁦2026-08-29⁩Forecast: ⁦2026-11-13⁩ → ⁦2027-01-12⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-03-21⁩ → ⁦2026-06-28⁩Forecast: ⁦2026-11-13⁩ → ⁦2026-12-20⁩Float: ⁦0⁩d+175
User acceptance testingPlanned: ⁦2026-05-22⁩ → ⁦2026-08-29⁩Forecast: ⁦2026-12-06⁩ → ⁦2027-01-12⁩Float: ⁦0⁩d+136
Testing & acceptance completePlanned: ⁦2026-08-29⁩ → ⁦2026-08-29⁩Forecast: ⁦2027-01-12⁩ → ⁦2027-01-12⁩Float: ⁦46⁩dTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-07-23⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-29⁩ → ⁦2027-02-27⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-07-23⁩ → ⁦2026-10-30⁩Forecast: ⁦2026-12-29⁩ → ⁦2027-02-04⁩Float: ⁦0⁩d+97
Go-live & handoverPlanned: ⁦2026-09-23⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-21⁩ → ⁦2027-02-27⁩Float: ⁦0⁩d+58
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-02-27⁩ → ⁦2027-02-27⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦8⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦5⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦0⁩ more activities have three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Integrations” needs a pace ⁦4.0⁩× faster than it has kept

It earned ⁦70%⁩ in 283 days; the forecast assumes the rest in 30 days. At the pace so far it finishes on ⁦2027-02-26⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 135 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

96
170
214
136
58
G1G2G3G4G5

The critical chain

In date order, to final acceptance