Enterprise Resource Planning (ERP) System
Remove from watchlistOne integrated system for finance, procurement and HR, connected to the Etimad platform.
Budget (BAC)
Actual cost
69% of budget
Progress
Planned 74%
Estimate at completion
SAR +8.8M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-22 | 2025-09-26 | +96 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-24 | 2026-04-12 | +170 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-04-27 | 2026-11-27 | +214 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-29 | 2027-01-12 | +136 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-02-27 | +58 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline001-D1 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | Munirah A. Al-Khalidi | 2025-04-21 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting001-D2 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.sa | Munirah A. Al-Khalidi | 2025-06-22 | V1 | 2 of 2 |
| Deliverable: Business requirements001-D3 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.sa | Munirah A. Al-Khalidi | 2025-08-23 | V1 | 2 of 2 |
| Deliverable: Solution design001-D4 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVP, Support ServicesP-012s.alqarni@alwaha.gov.sa | Munirah A. Al-Khalidi | 2025-10-24 | V1 | 2 of 2 |
| Deliverable: Release 1001-D5 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVP, Support ServicesP-012s.alqarni@alwaha.gov.sa | Munirah A. Al-Khalidi | 2025-12-25 | V1 | 2 of 2 |
| Deliverable: Release 2001-D6 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | Munirah A. Al-Khalidi | 2026-02-25 | V1 | 2 of 2 |