Programme · PG-04 · Technology Projects Portfolio

Enterprise Systems Programme

Off track

ERP, asset management, documents and employee self-service.

Approved budget
SAR 118.1M

incl. SAR 4M programme reserve

Actual spend
SAR 70.4M

⁦60%⁩ of budget

EAC
SAR 122.3M+7.1%

Estimate at completion

Progress
⁦58%⁩

Planned ⁦66%⁩

Schedule performance index
0.89

Cost performance index 0.94

Manager

Dana S. Al-Saleh

Director, Enterprise Applications

Sponsor

Sarah A. Al-Qarni

VP, Support Services

Projects

4 projects

2024-05-05 — 2027-12-30

On track 2At risk 1Off track 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    One ERP for finance, procurement, HR and assets

  2. 2

    A monthly financial close within 5 working days

  3. 3

    Self-service for 90% of employee transactions

Programme benefits

From baseline to target

  • Spend-rationalisation savings

    by ⁦2027⁩
    Baseline 0Current 61 SAR MTarget 85
  • Staff hours saved by automation

    by ⁦2027⁩
    Baseline 0Current 3,450 hoursTarget 3,600

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2024202520262027
2025-09-21
2027-02-27
2026-11-15
2027-12-30

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    Asset management needs the ERP finance module and asset register

  • Self-service processes fold into the HR module

  • Payment documents are archived from the correspondence system

Shared risks

Risks that hit more than one project, managed at programme level.

16

Late historic finance-data migration delays close and assets

PRK-04-1·Mitigate·Dana S. Al-Saleh

Affects
9

Resistance from users of paper processes

PRK-04-2·Mitigate·Nouf M. Al-Balawi

Affects

Open risks in the programme’s projects

4 risks

Open risks in the programme’s projects
  • Critical0
  • High1
  • Medium3
  • Low0
  • Risks 4
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium1 · Medium1 · High0 · Critical
30 · Low0 · Low2 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely3

Monitor0

Keep informed1

Sarah A. Al-QarniManage closelyMunirah A. Al-KhalidiManage closelyAbdulmajeed R. Al-DosariManage closelyHaifa S. Al-RuwailiKeep informed

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & Technology
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-11-03
PMO Committee

Fortnightly · Quorum ⁦4⁩

Faisal A. Al-Shehri · Digital Transformation Portfolio ManagerDr. Amal F. Al-Sudairi · Deputy, Strategic Planning & PerformanceTariq S. Al-Yami · Director, Corporate Performance Measurement
Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04
Change Control Board

Weekly · Quorum ⁦4⁩

Dr. Noura M. Al-Otaibi · Director, Enterprise PMOKhalid N. Al-Mutairi · Senior Finance & Contracts SpecialistMunirah A. Al-Khalidi · Deputy, Financial Affairs
Chair: Dr. Mohammed I. Al-SubaieNext meeting 2026-10-29

Programme projects

The programme’s performance is computed from these projects (§6).

⁦4⁩ results
Export CSV
Manager
Enterprise Resource Planning (ERP) SystemPRJ-2026-001Dana S. Al-Saleh7ExecutionOff track⁦61%⁩64.5M73.3M⁦+13.6%⁩0.82Schedule performance index · 0.820.88Cost performance index · 0.88
Smart Asset Management SystemPRJ-2026-011Dana S. Al-Saleh4PlanningOn track⁦6%⁩24M24M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Document & Correspondence Management PlatformPRJ-2026-017Dana S. Al-Saleh9HandoverAt risk⁦95%⁩14.2M14.2M⁦0.0%⁩0.95Schedule performance index · 0.951.00Cost performance index · 1.00
HR Self-Service AutomationPRJ-2026-032Dana S. Al-Saleh11Benefits RealizationOn track⁦100%⁩11.4M10.8M⁦−5.7%⁩1.00Schedule performance index · 1.001.06Cost performance index · 1.06
Total · 4114.1M122.3M
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SAR 114.1M

Budget

  • Enterprise Resource Planning (ERP) SystemSAR 64.5M⁦57%⁩
  • Smart Asset Management SystemSAR 24M⁦21%⁩
  • Document & Correspondence Management PlatformSAR 14.2M⁦12%⁩
  • HR Self-Service AutomationSAR 11.4M⁦10%⁩
Budget shares
CategoryValueShare
Enterprise Resource Planning (ERP) SystemSAR 64.5M⁦57%⁩
Smart Asset Management SystemSAR 24M⁦21%⁩
Document & Correspondence Management PlatformSAR 14.2M⁦12%⁩
HR Self-Service AutomationSAR 11.4M⁦10%⁩
TotalSAR 114.1M⁦100%⁩