Enterprise Resource Planning (ERP) System
Remove from watchlistOne integrated system for finance, procurement and HR, connected to the Etimad platform.
Budget (BAC)
Actual cost
69% of budget
Progress
Planned 74%
Estimate at completion
SAR +8.8M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate26 July 2024All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Mandatory criteria met, with points to close during the next phase.FeasibilityComplete
- Gate into «Planning»DecisionConditional goDate12 January 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
- Gate into «Approval»DecisionGoDate17 February 2025All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate10 March 2025All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionConditional goDate7 May 2025Mandatory criteria met, with points to close during the next phase.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 3 required documents not approved
- 1 mandatory criteria under 70 points
Checklist
5 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Staff trained
- Launch rollback plan
Required documents
1 of 4 approved
- UAT reportNot submitted
- Penetration test reportSubmitted — awaiting acceptance · V1
- Operations & support planSubmitted — awaiting acceptance · V1
- Data migration reconciliationApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Not met
Awaiting evidence from the project team.
Quality & securityweight 30%Met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Eng. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Sarah A. Al-QarniProject sponsorVote pending
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Munirah A. Al-KhalidiBusiness ownerVote pending