10My actionsNotifications
PRJ-2026-001Off track7ExecutionHybrid

Enterprise Resource Planning (ERP) System

Remove from watchlist

One integrated system for finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩

Planned ⁦74%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control21 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−23

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦86%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.82⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦61%⁩ done against ⁦74%⁩ planned.

SPI ⁦0.82⁩, CPI ⁦0.88⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦81%⁩ of budget

44.7M/ 64.5M8.8Mprojected overrun(⁦13.6%⁩)
Actual spend
44.7M
Committed
52.4M
Approved budget
64.5M
Estimate at completion
73.3M

Next milestones

  • Provisional acceptance⁦2026-12-18⁩was ⁦2026-11-04⁩Late
  • Closure⁦2027-02-27⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦2⁩ approvals and ⁦2⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦2⁩ open

  • Re-baseline the plan per committee commentsDana S. Al-SalehIn 7 days2026-11-0424 Jumada I 1448 AHHigh
  • Joint fix session with the Etimad teamEng. Asma S. Al-HamdanIn 2 days2026-10-3019 Jumada I 1448 AHHigh

Risks & issues

3 open risks, exposure SAR 9.8M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0013Late migration and reconciliation of historical financial data1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0012Customisation and Etimad integration costs exceeding the approved contingencyProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0014Implementation consultants’ contracts ending before go-liveProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium2
  • Low0

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-001-1 · V1Dana S. Al-Saleh⁦2025-02-10⁩2025-02-1011 Shaʻban 1446 AHApproved
  • Main deliverable — stage 1DLV-001-2 · V1Munirah A. Al-Khalidi⁦2026-01-13⁩2026-01-1324 Rajab 1447 AHApproved
  • Main deliverable — final stageDLV-001-3 · V1Munirah A. Al-Khalidi37 days overdue2026-09-2110 Rabiʻ II 1448 AHIn review
  • Final reportDLV-001-4 · V1Munirah A. Al-KhalidiIn 64 days2026-12-3122 Rajab 1448 AHIn progress

Team, contracts & documents

Team

4 members

Dana S. Al-Saleh · Director, Enterprise ApplicationsEng. Asma S. Al-Hamdan · Enterprise ArchitectHaifa S. Al-Ruwaili · Senior Financial Analyst
  • Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsProject managerP-025d.alsaleh@alwaha.gov.sa⁦60%⁩
  • Eng. Asma S. Al-HamdanEng. Asma S. Al-HamdanEnterprise ArchitectERP solution architectureP-031a.alhamdan@alwaha.gov.sa⁦40%⁩
  • Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystFinancial analystP-037h.alruwaili@alwaha.gov.sa⁦10%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close