PRJ-2026-001Off track7ExecutionHybrid
Enterprise Resource Planning (ERP) System
Remove from watchlistOne integrated system for finance, procurement and HR, connected to the Etimad platform.
Early warning: 86% chance of slipping within 30 days
Budget (BAC)
SAR 64.5M
Actual cost
SAR 44.7M
69% of budget
Progress
61%
Planned 74%
Estimate at completion
SAR 73.3M
SAR +8.8M
SPI · CPI
0.82Schedule performance index · 0.820.88Cost performance index · 0.88
Forecast finish
2027-02-27
58 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work62.6M16 elements
Unallocated contingency1.9MSAR 3.2M
Budget at completion64.5MPRJ-2026-001
Weighted progress61%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total61%62.5744.71