Enterprise Resource Planning (ERP) System

Remove from watchlist

One integrated system for finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩

Planned ⁦74%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control21 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate26 July 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate17 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate7 May 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate21 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Al-Waha Region Development Authority

Project charter

Enterprise Resource Planning (ERP) System

APPROVEDV2Approved ⁦2025-01-10⁩

1Project identity

Project name
Enterprise Resource Planning (ERP) System
Project code
PRJ-2026-001
Sponsor
Sarah A. Al-QarniSarah A. Al-QarniVP, Support ServicesP-012s.alqarni@alwaha.gov.sa
Project manager
Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa
Business owner
Munirah A. Al-KhalidiMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.sa
Portfolio & programme
Technology Projects PortfolioEnterprise Systems Programme
Type & methodology
IT · Hybrid
Current phase
7Execution

2Background & rationale

One integrated system for finance, procurement and HR, connected to the Etimad platform.

3Objectives

  1. 1Spend efficiently and grow own revenues
  2. 2Embed project governance and performance management

4Scope

In scope

  • One integrated system for finance, procurement and HR, connected to the Etimad platform.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3Essential cybersecurity controls

6Deliverables

1Project management plan⁦2025-02-10⁩
2Main deliverable — stage 1⁦2026-01-13⁩
3Main deliverable — final stage⁦2026-09-21⁩
4Final report⁦2026-12-31⁩

7Key milestones

  1. Charter approved⁦2025-01-10⁩
  2. Contract signed⁦2025-05-07⁩
  3. 50% of works complete⁦2026-01-13⁩
  4. Provisional acceptance⁦2026-11-04⁩
  5. Closure⁦2026-12-31⁩

8Budget

  • Main contract⁦71.9%⁩46.4M
  • Supervision & consulting⁦14.1%⁩9.1M
  • Internal team⁦9.0%⁩5.8M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩3.2M
The owning sector’s approved budgetTotal64.5M

9Timeline

Start
2025-01-1212 Rajab 1446 AH
Baseline finish
2026-12-3122 Rajab 1448 AH
Duration
⁦24⁩ months

10Key risks

  • HighCustomisation and Etimad integration costs exceeding the approved contingency
  • MediumLate migration and reconciliation of historical financial data
  • MediumImplementation consultants’ contracts ending before go-live

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • PMOGovernance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly