Original
Original baseline
- Finish
- 2026-12-31
- Budget
- SAR 64.5M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-01-12 · by Sarah A. Al-Qarni
One integrated system for finance, procurement and HR, connected to the Etimad platform.
Budget (BAC)
Actual cost
69% of budget
Progress
Planned 74%
Estimate at completion
SAR +8.8M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-01-12 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Dana S. Al-Saleh
What changed from version A to version B
Finish
2026-12-312027-02-27
+58 days
Budget
SAR 64.5MSAR 71.3M
+6.80 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference