Board of GrievancesMunjaz10My actionsNotifications

RSK-0042Board Cybersecurity Programme

Undetected vulnerabilities in legacy systems before SOC onboarding

10MediumIn progress

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Legacy systems holding classified case data without regular security patching

Preventive controls

  • A full vulnerability scan and fix the critical ones
  • Continuous monitoring from the SOC

2 / 2

Event

Undetected vulnerabilities in legacy systems before SOC onboarding

10MediumTrigger

An unpatched critical vulnerability found

Contingency

Isolate affected systems and run the response plan

Impact

Leaked party data, or a delayed NCA ECC compliance sign-off

SAR 3M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
10Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 3M

Residual

⁦60⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 2 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Yasser M. Al-Zahrani

    Currently followed up here
  2. 2

    Programme manager

    Eng. Omar H. Bawazir

  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • A full vulnerability scan and fix the critical ones

    Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa
    In progressIn 34 days2026-12-0121 Jumada II 1448 AH
  • Continuous monitoring from the SOC

    Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa
    Not startedIn 34 days2026-12-0121 Jumada II 1448 AH

Trigger

An unpatched critical vulnerability found

Contingency

Isolate affected systems and run the response plan

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close