A security operations centre, identity & access management and full ECC compliance.
Budget (BAC)
Actual cost
85% of budget
Progress
Planned 86%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Monitoring & ControlPhase 8 of 11
Next gate:Handover22 October 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
87
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 12% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 88% done against 86% planned.
SPI 1.02, CPI 1.03.
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 91% of budget
0 approvals and 0 open actions on this project
1 open risk, exposure SAR 3M
Impact
0 escalated
2 of 4 approved
2 members
1 contract