Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-005On track8Monitoring & ControlWaterfall

Board Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩

Planned ⁦86%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover22 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate8 March 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate28 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate22 May 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate22 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Board Cybersecurity Programme

APPROVEDV2Approved ⁦2025-01-31⁩

1Project identity

Project name
Board Cybersecurity Programme
Project code
PRJ-2026-005
Sponsor
Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa
Project manager
Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa
Business owner
Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa
Portfolio & programme
Technology & Enterprise Systems PortfolioDigital Infrastructure Programme
Type & methodology
IT · Waterfall
Current phase
8Monitoring & Control

2Background & rationale

A security operations centre, identity & access management and full ECC compliance.

3Objectives

  1. 1Build secure, reliable, cloud-first technology

4Scope

In scope

  • A security operations centre, identity & access management and full ECC compliance.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3Essential cybersecurity controls

6Deliverables

1Project management plan⁦2025-03-01⁩
2Main deliverable — stage 1⁦2026-01-16⁩
3Main deliverable — final stage⁦2026-09-11⁩
4Final report⁦2026-12-15⁩

7Key milestones

  1. Charter approved⁦2025-01-31⁩
  2. Contract signed⁦2025-05-22⁩
  3. 50% of works complete⁦2026-01-16⁩
  4. Provisional acceptance⁦2026-10-22⁩
  5. Closure⁦2026-12-15⁩

8Budget

  • Main contract⁦72.0%⁩27.8M
  • Supervision & consulting⁦14.0%⁩5.4M
  • Internal team⁦9.1%⁩3.5M
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩1.9M
The owning sector’s approved budgetTotal38.6M

9Timeline

Start
2025-02-023 Shaʻban 1446 AH
Baseline finish
2026-12-156 Rajab 1448 AH
Duration
⁦22⁩ months

10Key risks

  • MediumUndetected vulnerabilities in legacy systems before SOC onboarding

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close