PRJ-2026-005On track8Monitoring & ControlWaterfall
Board Cybersecurity Programme
Add to watchlistA security operations centre, identity & access management and full ECC compliance.
Project managerEng. Yasser M. Al-ZahraniSponsorEng. Majed S. Al-RasheedProgrammeDigital Infrastructure Programme
Budget (BAC)
SAR 38.6M
Actual cost
SAR 33M
85% of budget
Progress
88%
Planned 86%
Estimate at completion
SAR 37.5M
SPI · CPI
1.02Schedule performance index · 1.021.03Cost performance index · 1.03
Forecast finish
2026-12-10
On baseline
Monitoring & ControlPhase 8 of 11
Next gate:Handover22 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 August 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate8 March 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionConditional goDate28 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate22 May 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
- Gate into «Handover»DecisionNot held yetDate22 October 2026Handover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work37.4M16 elements
Unallocated contingency1.2MSAR 1.9M
Budget at completion38.6MPRJ-2026-005
Weighted progress88%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total88%37.4432.98