Board Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩

Planned ⁦86%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover22 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate8 March 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate28 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate22 May 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate22 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
1On track
0At risk
0Late
Average delay38 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-04-24⁩Forecast / actual: ⁦2026-06-18⁩Delay: 55 daysG3 +55
Executive
Project plan approvedPlanned: ⁦2025-07-05⁩Forecast / actual: ⁦2025-07-23⁩Delay: 18 daysG1 +18
Payment
Final handoverPlanned: ⁦2026-12-15⁩Forecast / actual: ⁦2027-01-02⁩Delay: 18 daysG5 +18
Regulatory
Testing & acceptance completePlanned: ⁦2026-08-20⁩Forecast / actual: ⁦2026-10-26⁩Delay: 67 daysG4 +67
Project
Designs approvedPlanned: ⁦2025-10-30⁩Forecast / actual: ⁦2025-12-02⁩Delay: 33 daysG2 +33

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-07-05⁩⁦2025-07-23⁩⁦+18⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-10-30⁩⁦2025-12-02⁩⁦+33⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-04-24⁩⁦2026-06-18⁩⁦+55⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-08-20⁩⁦2026-10-26⁩⁦+67⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-12-15⁩⁦2027-01-02⁩⁦+18⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline005-D1ApprovedEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saEng. Nayef H. Al-Buqami⁦2025-05-07⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting005-D2ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.saEng. Nayef H. Al-Buqami⁦2025-07-05⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Business requirements005-D3ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.saEng. Nayef H. Al-Buqami⁦2025-09-01⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Solution design005-D4ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.saEng. Nayef H. Al-Buqami⁦2025-10-30⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 1005-D5ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.saEng. Nayef H. Al-Buqami⁦2025-12-28⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 2005-D6ApprovedEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saEng. Nayef H. Al-Buqami⁦2026-02-24⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close