Judicial Systems Migration to the Government Cloud
Add to watchlistMove 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.
Budget (BAC)
Actual cost
48% of budget
Progress
Planned 53%
Estimate at completion
SAR +1.6M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control1 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-10-22 | 2026-01-25 | +95 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-09 | 2026-07-28 | +169 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-23 | 2026-12-20 | +150 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-10 | 2027-02-02 | +84 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-02-28 | 2027-03-18 | +18 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline009-D1 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-08-28 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting009-D2 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-10-22 | V1 | 2 of 2 |
| Deliverable: Business requirements009-D3 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-12-16 | V1 | 2 of 2 |
| Deliverable: Solution design009-D4 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-02-09 | V1 | 2 of 2 |
| Deliverable: Release 1009-D5 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-04-05 | V1 | 2 of 2 |
| Deliverable: Release 2009-D6 | Under review | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-05-29 | V1 | 1 of 2 |