PRJ-2026-009At risk7ExecutionHybrid

Judicial Systems Migration to the Government Cloud

Add to watchlist

Move 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩

Planned ⁦53%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control1 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work50.4M⁦16⁩ elements
Unallocated contingency1.6MSAR 2.6M
Budget at completion52MPRJ-2026-009
Weighted progress⁦47%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project655⁦2025-06-01⁩⁦2027-03-18⁩⁦47%⁩50.4425.20—
1
Phase238⁦2025-06-01⁩⁦2026-01-25⁩⁦100%⁩4.044.29—
1.1
WBS element147⁦2025-06-01⁩⁦2025-10-26⁩⁦100%⁩2.022.140 / 1
1.2
WBS element146⁦2025-09-01⁩⁦2026-01-25⁩⁦100%⁩2.022.141 / 2
2
Phase239⁦2025-12-01⁩⁦2026-07-28⁩⁦100%⁩8.579.11—
2.1
WBS element147⁦2025-12-01⁩⁦2026-04-27⁩⁦100%⁩4.294.561 / 1
2.2
WBS element147⁦2026-03-03⁩⁦2026-07-28⁩⁦100%⁩4.294.561 / 2
3
Phase292⁦2026-03-03⁩⁦2026-12-20⁩⁦55%⁩20.1811.79—
3.1
WBS element146⁦2026-06-03⁩⁦2026-10-27⁩⁦100%⁩6.737.151 / 1
3.2
WBS element270⁦2026-03-03⁩⁦2026-11-28⁩⁦65%⁩6.734.651 / 1
3.3
WBS element36⁦2026-11-14⁩⁦2026-12-20⁩⁦0%⁩6.73—1 / 2
4
Phase58⁦2026-12-06⁩⁦2027-02-02⁩⁦0%⁩10.09——
4.1
WBS element36⁦2026-12-06⁩⁦2027-01-11⁩⁦0%⁩5.04—1 / 1
4.2
WBS element36⁦2026-12-28⁩⁦2027-02-02⁩⁦0%⁩5.04—1 / 2
5
Phase58⁦2027-01-19⁩⁦2027-03-18⁩⁦0%⁩7.57——
5.1
WBS element36⁦2027-01-19⁩⁦2027-02-24⁩⁦0%⁩3.78—1 / 1
5.2
WBS element36⁦2027-02-10⁩⁦2027-03-18⁩⁦0%⁩3.78—1 / 1
Total⁦47%⁩50.4425.20