PRJ-2026-009At risk7ExecutionHybrid

Judicial Systems Migration to the Government Cloud

Add to watchlist

Move 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩

Planned ⁦53%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control1 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+18⁩ days vs approved

Original baseline⁦2027-02-28⁩
Approved baseline⁦2027-02-28⁩
Current forecast⁦2027-03-18⁩
By earned schedule⁦2028-05-10⁩
Critical activities
7
of ⁦9⁩ open activities
Late activities
6
past their baseline finish
Schedule performance
0.52
earned ÷ planned value
Next milestone
in 53 days
Build complete
Expand allCollapse all
Activity
Judicial Systems Migration to the Government CloudPlanned: ⁦2025-06-01⁩ → ⁦2027-02-28⁩Forecast: ⁦2025-06-01⁩ → ⁦2027-03-18⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-06-01⁩ → ⁦2025-10-22⁩Actual: ⁦2025-06-01⁩ → ⁦2026-01-25⁩
Project plan & baselinePlanned: ⁦2025-06-01⁩ → ⁦2025-08-28⁩Actual: ⁦2025-06-01⁩ → ⁦2025-10-26⁩
Monitoring & reportingPlanned: ⁦2025-07-26⁩ → ⁦2025-10-22⁩Actual: ⁦2025-09-01⁩ → ⁦2026-01-25⁩
Project plan approvedPlanned: ⁦2025-10-22⁩ → ⁦2025-10-22⁩Actual: ⁦2026-01-25⁩ → ⁦2026-01-25⁩Project plan approved
Analysis & designPlanned: ⁦2025-09-19⁩ → ⁦2026-02-09⁩Actual: ⁦2025-12-01⁩ → ⁦2026-07-28⁩
Business requirementsPlanned: ⁦2025-09-19⁩ → ⁦2025-12-16⁩Actual: ⁦2025-12-01⁩ → ⁦2026-04-27⁩
Solution designPlanned: ⁦2025-11-13⁩ → ⁦2026-02-09⁩Actual: ⁦2026-03-03⁩ → ⁦2026-07-28⁩
Designs approvedPlanned: ⁦2026-02-09⁩ → ⁦2026-02-09⁩Actual: ⁦2026-07-28⁩ → ⁦2026-07-28⁩Designs approved
BuildPlanned: ⁦2026-01-07⁩ → ⁦2026-07-23⁩Forecast: ⁦2026-03-03⁩ → ⁦2026-12-20⁩Float: ⁦0⁩d
Release 1Planned: ⁦2026-01-07⁩ → ⁦2026-04-05⁩Actual: ⁦2026-06-03⁩ → ⁦2026-10-27⁩
Release 2Planned: ⁦2026-03-03⁩ → ⁦2026-05-29⁩Forecast: ⁦2026-03-03⁩ → ⁦2026-11-28⁩Float: ⁦0⁩d+183
IntegrationsPlanned: ⁦2026-04-26⁩ → ⁦2026-07-23⁩Forecast: ⁦2026-11-14⁩ → ⁦2026-12-20⁩Float: ⁦0⁩d+150
Build completePlanned: ⁦2026-07-23⁩ → ⁦2026-07-23⁩Forecast: ⁦2026-12-20⁩ → ⁦2026-12-20⁩Float: ⁦88⁩dBuild complete
Testing & acceptancePlanned: ⁦2026-06-20⁩ → ⁦2026-11-10⁩Forecast: ⁦2026-12-06⁩ → ⁦2027-02-02⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-06-20⁩ → ⁦2026-09-16⁩Forecast: ⁦2026-12-06⁩ → ⁦2027-01-11⁩Float: ⁦0⁩d+117
User acceptance testingPlanned: ⁦2026-08-14⁩ → ⁦2026-11-10⁩Forecast: ⁦2026-12-28⁩ → ⁦2027-02-02⁩Float: ⁦0⁩d+84
Testing & acceptance completePlanned: ⁦2026-11-10⁩ → ⁦2026-11-10⁩Forecast: ⁦2027-02-02⁩ → ⁦2027-02-02⁩Float: ⁦44⁩dTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-10-08⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-01-19⁩ → ⁦2027-03-18⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-10-08⁩ → ⁦2027-01-04⁩Forecast: ⁦2027-01-19⁩ → ⁦2027-02-24⁩Float: ⁦0⁩d+51
Go-live & handoverPlanned: ⁦2026-12-02⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-02-10⁩ → ⁦2027-03-18⁩Float: ⁦0⁩d+18
Final handoverPlanned: ⁦2027-02-28⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-03-18⁩ → ⁦2027-03-18⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦9⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦6⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Release 2” needs a pace ⁦4.2⁩× faster than it has kept

It earned ⁦65%⁩ in 239 days; the forecast assumes the rest in 31 days. At the pace so far it finishes on ⁦2027-03-06⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 125 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

95
169
150
84
G1G2G3G4

The critical chain

In date order, to final acceptance