Judicial Systems Migration to the Government Cloud
Add to watchlistMove 46 judicial and administrative systems to the government cloud under the classification framework and cloud controls.
Budget (BAC)
Actual cost
48% of budget
Progress
Planned 53%
Estimate at completion
SAR +1.6M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control1 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate13 December 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate3 July 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate22 July 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate11 September 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate1 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth