PRJ-2026-033On hold4PlanningConstruction

Regional Emergency & Safety Centre

Add to watchlist

A regional emergency-response hub with an operations room, training grounds and supply depots.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval13 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate12 September 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate13 April 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−14

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦2%⁩ done against ⁦2%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.00⁩.

Progress & earned value

⁦2⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦2%⁩ of budget

4.2M/ 210M
Actual spend
4.2M
Committed
4.6M
Approved budget
210M
Estimate at completion
210M

Next milestones

  • 50% of works complete⁦2027-08-10⁩was ⁦2027-05-10⁩Late
  • Provisional acceptance⁦2028-09-08⁩was ⁦2028-04-23⁩Late
  • Closure⁦2028-12-31⁩was ⁦2028-06-30⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 12M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0044Late land handover and title deed from the owning entityProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High0
  • Medium0
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦1⁩ of ⁦4⁩ approved

  • Project management planDLV-033-1 · V1Eng. Shahad M. Al-Malki⁦2026-04-04⁩2026-04-0416 Shawwal 1447 AHApproved
  • Main deliverable — stage 1DLV-033-2 · V0Eng. Abdulrahman S. Al-HarbiIn 194 days2027-05-104 Dhuʻl-Hijjah 1448 AHDraft
  • Main deliverable — final stageDLV-033-3 · V0Eng. Abdulrahman S. Al-HarbiIn 492 days2028-03-037 Shawwal 1449 AHDraft
  • Final reportDLV-033-4 · V0Eng. Abdulrahman S. Al-HarbiIn 611 days2028-06-307 Safar 1450 AHDraft

Team, contracts & documents

Team

1 member

Eng. Shahad M. Al-Malki · Director, Government Buildings & Facilities
  • Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesProject manager (on hold)P-022s.almalki@alwaha.gov.sa⁦10%⁩

Contracts

0 contracts

  • No external contracts — delivered in-house

Documents

  • No documents yet