PRJ-2026-033On hold4PlanningConstruction

Digital Administrative Court HQ, Wadi Al-Dawasir

Add to watchlist

A permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval13 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate12 September 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate13 April 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
0On track
4At risk
1Late
Average delay182 days
Oct 26Jan 27Apr 27Jul 27Oct 27Jan 28Apr 28Jul 28Oct 28Jan 29
Contractual
Build completePlanned: ⁦2027-07-28⁩Forecast / actual: ⁦2028-01-26⁩Delay: 182 daysG3 +182
Executive
Project plan approvedPlanned: ⁦2026-08-24⁩Forecast / actual: ⁦2027-02-15⁩Delay: 175 daysG1 +175
Payment
Final handoverPlanned: ⁦2028-06-30⁩Forecast / actual: ⁦2029-01-05⁩Delay: 189 daysG5 +189
Regulatory
Testing & acceptance completePlanned: ⁦2028-02-16⁩Forecast / actual: ⁦2028-08-20⁩Delay: 186 daysG4 +186
Project
Designs approvedPlanned: ⁦2027-01-06⁩Forecast / actual: ⁦2027-07-03⁩Delay: 178 daysG2 +178

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-08-24⁩⁦2027-02-15⁩⁦+175⁩ daysEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saLate0Not requested
Designs approvedMS-G2Project⁦2027-01-06⁩⁦2027-07-03⁩⁦+178⁩ daysEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saAt risk0Not requested
Build completeMS-G3Contractual⁦2027-07-28⁩⁦2028-01-26⁩⁦+182⁩ daysEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2028-02-16⁩⁦2028-08-20⁩⁦+186⁩ daysEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2028-06-30⁩⁦2029-01-05⁩⁦+189⁩ daysEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline033-D1SubmittedEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2026-06-17⁩V1⁦1⁩ of ⁦2⁩
Deliverable: Monitoring & reporting033-D2DraftEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2026-08-24⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Detailed design033-D3DraftEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2026-10-30⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Permits & approvals033-D4DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2027-01-06⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Site works & excavation033-D5DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2027-03-15⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Structure033-D6DraftEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2027-05-21⁩V0⁦0⁩ of ⁦2⁩