Digital Administrative Court HQ, Wadi Al-Dawasir
Add to watchlistA permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
184 days behind baseline
PlanningPhase 4 of 11
Next gate:Approval13 April 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate12 September 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 March 2026Planning · Current phasePlanning · Current phase
- Gate into «Approval»DecisionNot held yetDate13 April 2026Approval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-08-24 | 2027-02-15 | +175 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Late | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-01-06 | 2027-07-03 | +178 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-28 | 2028-01-26 | +182 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-02-16 | 2028-08-20 | +186 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-06-30 | 2029-01-05 | +189 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline033-D1 | Submitted | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2026-06-17 | V1 | 1 of 2 |
| Deliverable: Monitoring & reporting033-D2 | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2026-08-24 | V0 | 0 of 2 |
| Deliverable: Detailed design033-D3 | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-30 | V0 | 0 of 2 |
| Deliverable: Permits & approvals033-D4 | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2027-01-06 | V0 | 0 of 2 |
| Deliverable: Site works & excavation033-D5 | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2027-03-15 | V0 | 0 of 2 |
| Deliverable: Structure033-D6 | Draft | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2027-05-21 | V0 | 0 of 2 |