PRJ-2026-033On hold4PlanningConstruction

Digital Administrative Court HQ, Wadi Al-Dawasir

Add to watchlist

A permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval13 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate12 September 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate13 April 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2028-12-31⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Eng. Abdulrahman S. Al-HarbiPlanned ⁦2028-12-21⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Khalid N. Al-MutairiPlanned ⁦2029-01-20⁩

  3. 3

    Contract closureNot started

    Contracts closed, retention released

    Khalid N. Al-MutairiPlanned ⁦2029-01-30⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Eng. Shahad M. Al-MalkiPlanned ⁦2029-01-25⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Eng. Shahad M. Al-MalkiPlanned ⁦2029-01-15⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Eng. Abdulrahman S. Al-HarbiPlanned ⁦2029-01-10⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Eng. Shahad M. Al-MalkiPlanned ⁦2029-02-04⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2028-12-31⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.