Digital Administrative Court HQ, Wadi Al-Dawasir
Add to watchlistA permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
184 days behind baseline
PlanningPhase 4 of 11
Next gate:Approval13 April 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate12 September 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 March 2026Planning · Current phasePlanning · Current phase
- Gate into «Approval»DecisionNot held yetDate13 April 2026Approval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
A permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.
In scope
- A permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.
- Saudi Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2026-04-09
Baseline approved at the planning gate
Budget210MFinish2028-06-30
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
0%
0/6 · linked to a deliverable, task and test
Test passed
0%
0/6 · test result is a pass
Accepted
0%
0/6 · signed off by the business owner
Display options
| REQ-033-01 | A building ready for hearings | Business | Must | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-033-02 | Match the approved drawings | Technical | Must | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | SB-1 | |
| REQ-033-03 | Smart building systems | Functional | Must | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-033-04 | Saudi Building Code | Regulatory | Could | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | SB-1 | |
| REQ-033-05 | Health & safety | Regulatory | Should | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-033-06 | CCTV and access control | Security | Should | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. 6 requirements have a gap.