Original
Original baseline
- Finish
- 2028-06-30
- Budget
- SAR 210M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2026-03-01 · by Eng. Turki A. Al-Anazi
A permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
184 days behind baseline
PlanningPhase 4 of 11
Next gate:Approval13 April 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2026-03-01 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Shahad M. Al-Malki
What changed from version A to version B
Finish
2028-06-302029-01-05
+189 days
Budget
SAR 210MSAR 210M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference