PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 120 buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−19

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦8%⁩ done against ⁦9%⁩ planned.

SPI ⁦0.89⁩, CPI ⁦1.00⁩.

Progress & earned value

⁦2⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦9%⁩ of budget

2.6M/ 33M
Actual spend
2.6M
Committed
3.1M
Approved budget
33M
Estimate at completion
33M

Next milestones

  • 50% of works complete⁦2026-12-22⁩was ⁦2026-10-21⁩Late
  • Provisional acceptance⁦2027-08-20⁩was ⁦2027-05-20⁩Late
  • Closure⁦2027-10-31⁩was ⁦2027-06-30⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • Request ESCO funding in the ⁦2027⁩ budgetHaifa S. Al-RuwailiIn 18 days2026-11-155 Jumada II 1448 AHMedium

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 4.8M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0043Funding left out of the 2027 budget, keeping the tender suspendedProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium0
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-026-1 · V1Eng. Mishari K. Al-Otaibi⁦2026-02-22⁩2026-02-225 Ramadan 1447 AHApproved
  • Main deliverable — stage 1DLV-026-2 · V1Eng. Bandar M. Al-Shammari⁦2026-10-21⁩2026-10-2110 Jumada I 1448 AHApproved
  • Main deliverable — final stageDLV-026-3 · V0Eng. Bandar M. Al-ShammariIn 173 days2027-04-1912 Dhuʻl-Qiʻdah 1448 AHDraft
  • Final reportDLV-026-4 · V0Eng. Bandar M. Al-ShammariIn 245 days2027-06-3025 Muharram 1449 AHDraft

Team, contracts & documents

Team

3 members

Eng. Mishari K. Al-Otaibi · Director, Sustainability & EnvironmentRami Al-Khatib · Finance & PPP ConsultantMazen A. Al-Hazmi · Procurement & Tendering Specialist
  • Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & EnvironmentProject manager (on hold)P-028m.alotaibi@alwaha.gov.sa⁦15%⁩
  • Rami Al-KhatibRami Al-KhatibFinance & PPP ConsultantPPP adviser, ESCO modelP-045r.alkhatib@alwaha.gov.sa⁦25%⁩
  • Mazen A. Al-HazmiMazen A. Al-HazmiProcurement & Tendering SpecialistESCO tenderP-038m.alhazmi@alwaha.gov.sa⁦20%⁩

Contracts

0 contracts

  • No external contracts — delivered in-house