PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-06-30⁩
    Budget
    SAR 33M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2026-02-01⁩ · by Sarah A. Al-Qarni

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-10-31⁩
    ⁦+123⁩ days
    Budget
    SAR 33M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Mishari K. Al-Otaibi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-06-30⁩⁦2027-10-31⁩

⁦+123⁩ days

Budget

SAR 33MSAR 33M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-072027-012027-07
  • Project plan approved⁦+161⁩
  • Designs approved⁦+161⁩
  • Build complete⁦+147⁩
  • Testing & acceptance complete⁦+133⁩
  • Final handover⁦+123⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.06⁩
  • 2Design & permits⁦+0.05⁩
  • 3Civil works⁦+0.84⁩
  • 4MEP works⁦+0.14⁩
  • 5Handover⁦+0.07⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Mishari K. Al-Otaibi
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2026-02-01⁩by Sarah A. Al-Qarni