Original
Original baseline
- Finish
- 2027-06-30
- Budget
- SAR 33M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2026-02-01 · by Sarah A. Al-Qarni
HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.
Budget (BAC)
Actual cost
8% of budget
Progress
Planned 9%
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
ProcurementPhase 6 of 11
Next gate:Execution24 April 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2026-02-01 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Mishari K. Al-Otaibi
What changed from version A to version B
Finish
2027-06-302027-10-31
+123 days
Budget
SAR 33MSAR 33M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference