10My actionsNotifications

Programme · PG-09 · Sustainability Portfolio

Energy & Water Efficiency Programme

Off track

Water treatment and reuse, solar power, building efficiency and afforestation.

Approved budget
SAR 665M

incl. SAR 15M programme reserve

Actual spend
SAR 470.5M

⁦71%⁩ of budget

EAC
SAR 726M+11.7%

Estimate at completion

Progress
⁦64%⁩

Planned ⁦80%⁩

Schedule performance index
0.83

Cost performance index 0.90

Manager

Eng. Mishari K. Al-Otaibi

Director, Sustainability & Environment

Sponsor

Eng. Bandar M. Al-Shammari

Deputy, Infrastructure

Projects

5 projects

2024-01-14 — 2027-10-31

On track 3Critical 1On hold 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Reuse 55% of treated wastewater

  2. 2

    15% of government-building energy from renewables

  3. 3

    Cut emissions 12% from baseline

Programme benefits

From baseline to target

  • Treated water reused

    by ⁦2027⁩
    Baseline 38Current 43 %Target 55
  • Renewable energy share

    by ⁦2026⁩
    Baseline 4Current 14.1 %Target 15
  • Energy-bill savings

    by ⁦2027⁩
    Baseline 0Current 9.6 SAR MTarget 22

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2024202520262027
2027-02-03
2026-11-12
2027-04-22
2027-09-30
2027-10-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    Afforestation is irrigated with the plant’s treated water

  • The small dams feed the irrigation reservoirs

  • The retrofit builds on the solar metering

Shared risks

Risks that hit more than one project, managed at programme level.

16

A late plant leaves afforestation without irrigation in summer 2027

PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi

Affects

Open risks in the programme’s projects

5 risks

Open risks in the programme’s projects
  • Critical1
  • High2
  • Medium1
  • Low1
  • Risks 5
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical1 · Critical
40 · Low0 · Medium0 · Medium1 · High0 · Critical
30 · Low0 · Low0 · Medium1 · Medium1 · High
20 · Low0 · Low1 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied1

Manage closely3

Monitor0

Keep informed0

Eng. Bandar M. Al-ShammariManage closelyEng. Mishari K. Al-OtaibiManage closelyEng. Waleed O. Al-JuhaniManage closelySarah A. Al-QarniKeep satisfied

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & Technology
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & TechnologySarah A. Al-Qarni · VP, Support Services
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-10-28

Programme projects

The programme’s performance is computed from these projects (§6).

⁦5⁩ results
Export CSV
Manager
East Waha Wastewater Treatment PlantPRJ-2026-004Eng. Waleed O. Al-Juhani7ExecutionCritical⁦68%⁩412M490.5M⁦+19.0%⁩0.74Schedule performance index · 0.740.84Cost performance index · 0.84
Solar Power for Government BuildingsPRJ-2026-010Eng. Mishari K. Al-Otaibi7ExecutionOn track⁦58%⁩96M95.1M⁦−1.0%⁩1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Green Waha Urban AfforestationPRJ-2026-025Eng. Mishari K. Al-Otaibi7ExecutionOn track⁦36%⁩42M41.2M⁦−2.0%⁩1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Energy Retrofit of Existing Buildings (ESCO)PRJ-2026-026Eng. Mishari K. Al-Otaibi6ProcurementOn hold⁦8%⁩33M33M⁦0.0%⁩0.89Schedule performance index · 0.891.00Cost performance index · 1.00
Rainwater Harvesting & Small DamsPRJ-2026-036Eng. Waleed O. Al-Juhani9HandoverOn track⁦97%⁩67M66.3M⁦−1.0%⁩0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Total · 5650M726M
⁦1⁩–⁦5⁩ of ⁦5⁩

Budget shares

Budget shares

SAR 650M

Budget

  • East Waha Wastewater Treatment PlantSAR 412M⁦63%⁩
  • Solar Power for Government BuildingsSAR 96M⁦15%⁩
  • Green Waha Urban AfforestationSAR 42M⁦6%⁩
  • Energy Retrofit of Existing Buildings (ESCO)SAR 33M⁦5%⁩
  • Rainwater Harvesting & Small DamsSAR 67M⁦10%⁩
Budget shares
CategoryValueShare
East Waha Wastewater Treatment PlantSAR 412M⁦63%⁩
Solar Power for Government BuildingsSAR 96M⁦15%⁩
Green Waha Urban AfforestationSAR 42M⁦6%⁩
Energy Retrofit of Existing Buildings (ESCO)SAR 33M⁦5%⁩
Rainwater Harvesting & Small DamsSAR 67M⁦10%⁩
TotalSAR 650M⁦100%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close