A late plant leaves afforestation without irrigation in summer 2027
PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi
Programme · PG-09 · Sustainability Portfolio
Water treatment and reuse, solar power, building efficiency and afforestation.
incl. SAR 15M programme reserve
71% of budget
Estimate at completion
Planned 80%
Cost performance index 0.90
Manager
Eng. Mishari K. Al-Otaibi
Director, Sustainability & Environment
Sponsor
Eng. Bandar M. Al-Shammari
Deputy, Infrastructure
Projects
5 projects
2024-01-14 — 2027-10-31
On track 3Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
Reuse 55% of treated wastewater
15% of government-building energy from renewables
Cut emissions 12% from baseline
Serves strategic objectives
From baseline to target
Treated water reused
by 2027Renewable energy share
by 2026Energy-bill savings
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
Afforestation is irrigated with the plant’s treated water
The small dams feed the irrigation reservoirs
The retrofit builds on the solar metering
Risks that hit more than one project, managed at programme level.
A late plant leaves afforestation without irrigation in summer 2027
PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi
5 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 1 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 1 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Carbon emissions cut against baseline
9.7%
+1
Target 12.0%81%
Renewable share of government building energy
14.1%
+1
Target 15.0%94%
Treated wastewater reused
43%
0
Target 55%78%
Green space per capita
4.1m² per capita
0
Target 4.591%
Power against interest; click a person to see their role.
Keep satisfied1
Manage closely3
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
ESCO energy retrofit put on hold pending funding
Executive Committee · 2026-10-06 · DEC-2026-035
Solar for government buildings passes the mid-execution review
PMO Committee · 2026-09-30 · DEC-2026-034
Task force formed for the wastewater-plant contractor distress
Executive Committee · 2026-09-22 · DEC-2026-032
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
The programme’s performance is computed from these projects (§6).
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| East Waha Wastewater Treatment PlantPRJ-2026-004 | Eng. Waleed O. Al-Juhani | 7Execution | Critical | 68% | 412M | 490.5M+19.0% | 0.74Schedule performance index · 0.74 | 0.84Cost performance index · 0.84 |
| Solar Power for Government BuildingsPRJ-2026-010 | Eng. Mishari K. Al-Otaibi | 7Execution | On track | 58% | 96M | 95.1M−1.0% | 1.02Schedule performance index · 1.02 | 1.01Cost performance index · 1.01 |
| Green Waha Urban AfforestationPRJ-2026-025 | Eng. Mishari K. Al-Otaibi | 7Execution | On track | 36% | 42M | 41.2M−2.0% | 1.03Schedule performance index · 1.03 | 1.02Cost performance index · 1.02 |
| Energy Retrofit of Existing Buildings (ESCO)PRJ-2026-026 | Eng. Mishari K. Al-Otaibi | 6Procurement | On hold | 8% | 33M | 33M0.0% | 0.89Schedule performance index · 0.89 | 1.00Cost performance index · 1.00 |
| Rainwater Harvesting & Small DamsPRJ-2026-036 | Eng. Waleed O. Al-Juhani | 9Handover | On track | 97% | 67M | 66.3M−1.0% | 0.98Schedule performance index · 0.98 | 1.01Cost performance index · 1.01 |
| Total · 5 | 650M | 726M |
SAR 650M
Budget
| Category | Value | Share |
|---|---|---|
| East Waha Wastewater Treatment Plant | SAR 412M | 63% |
| Solar Power for Government Buildings | SAR 96M | 15% |
| Green Waha Urban Afforestation | SAR 42M | 6% |
| Energy Retrofit of Existing Buildings (ESCO) | SAR 33M | 5% |
| Rainwater Harvesting & Small Dams | SAR 67M | 10% |
| Total | SAR 650M | 100% |