The objective’s weakest KPI, “Treated wastewater reused”, is at 78% of its target, and its heaviest project, “East Waha Wastewater Treatment Plant”, is Critical. Fixing that one path lifts the objective more than any other action.
What we are doing to bring the KPI back on track, who owns it, and by when.
Run the temporary irrigation line from the rainwater-harvesting plant
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021·w.aljuhani@alwaha.gov.saDue 2026-10-253 days overdue2026-10-25·14 Jumada I 1448 AHK-1.2.3Rainwater Harvesting & Small Dams
Overdue
Settle the East Waha treatment-plant claim through the dispute board
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021·w.aljuhani@alwaha.gov.saDue 2026-11-15In 18 days2026-11-15·5 Jumada II 1448 AHK-1.2.3East Waha Wastewater Treatment Plant
In progress
Fast-track grid connection of the solar plants on 12 buildings
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & EnvironmentP-028·m.alotaibi@alwaha.gov.saDue 2026-12-15In 48 days2026-12-15·6 Rajab 1448 AHK-1.2.1Solar Power for Government Buildings
Open
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
The contractor claim at the East Waha treatment plant has stopped the transfer-line works — the main reason the reuse KPI is flat.
Eng. Waleed O. Al-Juhani · 2026-10-18
Note
The building retrofit is on hold pending the MoF-approved ESCO contract model.