AI insight
No early warning on this project
Only a 12% chance of a further slip on current trends.
Nine small dams and recharge channels to harvest rainwater in the highlands.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 99%
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure31 October 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
88
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 12% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 97% done against 99% planned.
SPI 0.98, CPI 1.01.
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 99% of budget
1 approvals and 0 open actions on this project
From «My actions» for this project
0 open
Cost and schedule impact
1 open risk, exposure SAR 600K
Impact
0 escalated
2 of 4 approved
1 member