Rainwater Harvesting & Small Dams
Add to watchlistNine small dams and recharge channels to harvest rainwater in the highlands.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 99%
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure31 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Closure readiness
Closure planned after the forecast finish on 2026-11-12
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Eng. Bandar M. Al-ShammariPlanned 2026-11-02
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2026-12-02
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2026-12-12
- 4
Documents archivedNot started
Documents archived with classification
Eng. Waleed O. Al-JuhaniPlanned 2026-12-07
- 5
Lessons learnedNot started
Lessons-learned session
Eng. Waleed O. Al-JuhaniPlanned 2026-11-27
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Eng. Bandar M. Al-ShammariPlanned 2026-11-22
- 7
Final report approvedNot started
Final report and its approval
Eng. Waleed O. Al-JuhaniPlanned 2026-12-17
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2026-11-12), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
- Rainwater harvested
baseline 0 · now 0 · target 4,800 thousand m³ / year
0% of target realisedHanded over at closure (current owner: Eng. Waleed O. Al-Juhani)