Rainwater Harvesting & Small Dams
Add to watchlistNine small dams and recharge channels to harvest rainwater in the highlands.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 99%
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure31 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
Nine small dams and recharge channels to harvest rainwater in the highlands.
In scope
- Nine small dams and recharge channels to harvest rainwater in the highlands.
- Saudi Building Code compliance
- Approved traffic diversion plan
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2024-11-09
Baseline approved at the planning gate
Budget67MFinish2026-10-31
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-036-01 | Reach the target capacity | Business | Must | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.sa | SB-1 | |
| REQ-036-02 | Meet the approved technical specs | Technical | Must | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | SB-1 | |
| REQ-036-03 | Traffic diversion plan | Functional | Must | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.sa | SB-1 | |
| REQ-036-04 | Saudi Building Code | Regulatory | Should | In progress | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | SB-1 | |
| REQ-036-05 | Civil-defence requirements | Regulatory | Should | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.sa | SB-1 | |
| REQ-036-06 | Site and systems security | Security | Could | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. 0 requirements have a gap.