PRJ-2026-036On track9HandoverConstruction
Rainwater Harvesting & Small Dams
Add to watchlistNine small dams and recharge channels to harvest rainwater in the highlands.
Project managerEng. Waleed O. Al-JuhaniSponsorEng. Turki A. Al-AnaziProgrammeEnergy & Water Efficiency Programme
Budget (BAC)
SAR 67M
Actual cost
SAR 64.3M
96% of budget
Progress
97%
Planned 99%
Estimate at completion
SAR 66.3M
SPI · CPI
0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Forecast finish
2026-11-12
12 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure31 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started