Rainwater Harvesting & Small Dams
Add to watchlistNine small dams and recharge channels to harvest rainwater in the highlands.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 99%
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure31 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Team & roles
1 member, about 0.3 full-time equivalents
Leadership
1 member
- Eng. Waleed O. Al-JuhaniProject manager30%Allocated 130% across all projectsA
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 5 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Turki A. Al-Anazi
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 steps — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Turki A. Al-Anazi | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | 2026-10-20 | |||
| Eng. Bandar M. Al-Shammari | Business owner | Accepts deliverables, owns benefits | SupportiveLeading | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | 2026-10-23 | |||
| Enterprise PMO | Governance | Compliance and data quality | Supportive | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | 2026-10-17 | |||
| Financial Affairs Agency | Internal department | Payment approval | NeutralSupportive | Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@alwaha.gov.sa | 2026-10-14 | |||
| United Water & Environment Co. | Main vendor | Delivers the contracted work | ResistantSupportive | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | 2026-10-24 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | 2026-09-26 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Waleed O. Al-Juhani2026-11-15
- Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Waleed O. Al-Juhani2026-11-03
- PMOData and indicator updatesWeeklyDashboardEng. Waleed O. Al-Juhani2026-10-31
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Waleed O. Al-JuhaniAt launch
Coming up
By date
- 312026-10PMODashboard · Weekly
- 032026-11Business ownerEmail · Fortnightly
- 152026-11Project sponsorMeeting · Monthly