PRJ-2026-036On track9HandoverConstruction

Rainwater Harvesting & Small Dams

Add to watchlist

Nine small dams and recharge channels to harvest rainwater in the highlands.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩

Planned ⁦99%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

HandoverPhase ⁦9⁩ of ⁦11⁩

Next gate:Closure31 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
  10. Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
0On track
1At risk
0Late
Average delay33 days
Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-01-04⁩Forecast / actual: ⁦2026-02-11⁩Delay: 38 daysG3 +38
Executive
Project plan approvedPlanned: ⁦2025-03-11⁩Forecast / actual: ⁦2025-03-24⁩Delay: 13 daysG1 +13
Payment
Final handoverPlanned: ⁦2026-10-31⁩Forecast / actual: ⁦2026-12-08⁩Delay: 38 daysG5 +38
Regulatory
Testing & acceptance completePlanned: ⁦2026-07-03⁩Forecast / actual: ⁦2026-08-24⁩Delay: 52 daysG4 +52
Project
Designs approvedPlanned: ⁦2025-07-09⁩Forecast / actual: ⁦2025-07-31⁩Delay: 22 daysG2 +22

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-03-11⁩⁦2025-03-24⁩⁦+13⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-07-09⁩⁦2025-07-31⁩⁦+22⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-01-04⁩⁦2026-02-11⁩⁦+38⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-07-03⁩⁦2026-08-24⁩⁦+52⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-10-31⁩⁦2026-12-08⁩⁦+38⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline036-D1ApprovedEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-01-10⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting036-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-03-11⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design036-D3ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-05-10⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals036-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-07-09⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation036-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-09-07⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure036-D6ApprovedEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-11-05⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close