Rainwater Harvesting & Small Dams
Add to watchlistNine small dams and recharge channels to harvest rainwater in the highlands.
Budget (BAC)
Actual cost
96% of budget
Progress
Planned 99%
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure31 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-03-11 | 2025-03-24 | +13 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-07-09 | 2025-07-31 | +22 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-01-04 | 2026-02-11 | +38 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-03 | 2026-08-24 | +52 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-10-31 | 2026-12-08 | +38 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline036-D1 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | Eng. Bandar M. Al-Shammari | 2025-01-10 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting036-D2 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.sa | Eng. Bandar M. Al-Shammari | 2025-03-11 | V1 | 2 of 2 |
| Deliverable: Detailed design036-D3 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.sa | Eng. Bandar M. Al-Shammari | 2025-05-10 | V1 | 2 of 2 |
| Deliverable: Permits & approvals036-D4 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.sa | Eng. Bandar M. Al-Shammari | 2025-07-09 | V1 | 2 of 2 |
| Deliverable: Site works & excavation036-D5 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.sa | Eng. Bandar M. Al-Shammari | 2025-09-07 | V1 | 2 of 2 |
| Deliverable: Structure036-D6 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | Eng. Bandar M. Al-Shammari | 2025-11-05 | V1 | 2 of 2 |